DELAY, DISRUPTION, DAMAGES, & DISTRESSED PROJECT RECOVERY EXPERTS

Building Projects

Our experts have extensive experience providing delay and quantum analyses for Commercial, Federal & Institutional Building projects; and providing independent assessments of owner and contractor claims.  As experts, they have analyzed and issued opinions for delay and quantum matters on billions of dollars in dispute for technically complex projects.

Airport

Guam – On behalf of the Construction Manager and Airport Authority, reviewed cost estimates of the main Contractor’s claims for extension of time and increased costs on the construction of Phase 1 expansion works for the Guam International Airport project. Under a second assignment on behalf of the Airport Authority, reviewed the main Contractor’s claims in international arbitration for delay and increased costs of performance on the construction of Phase 2 expansion works for the Guam International Airport project.

Kuwait – On behalf of the Contractor in dispute with the Owner, provided a delay analysis and damages calculation the reconstruction of the Kuwait El Jabar Air Force Base following the Desert Storm war.

Malaysia – On behalf of the Contractor for the main terminal building of the new-build Kuala Lumpur International Airport. Prepared a schedule delay analysis for an extension of time for delay to foundation works, prepared a revised baseline schedule, and provided on-site master schedule maintenance and project controls supervision for the remainder of the main terminal building contract duration to project completion.

Qatar – On behalf of the Contractor for the main terminal building at the Hamad International Airport, a US $4 billion project, prepared a revised baseline schedule under consulting contract. Then, employed to recover 16 months of delay within four months.

Qatar – On behalf of the mechanical subcontractor for the main terminal building of the Hamad International Airport, prepared a forensic schedule delay analysis to quantify the subcontractor’s entitlement for extension of time and recovery of increased costs of performance.

Qatar – On behalf of the special structural systems subcontractor for the Emiri terminal building at the Hamad International Airport, retained as a Commercial Manager to prepare and submit outstanding claims to the main contractor.

Switzerland – On behalf of the Contractor in international arbitration for an air defence system provided to the Iranian government, provided an independent expert quantum report. 

USA – On behalf of the baggage handling system subcontractor for the Philadelphia International Airport terminal building expansion program in arbitration, prepared an independent schedule delay analysis.

USA – On behalf of the contractor for the NASA Wallops Island runaway / apron renovation program in arbitration, prepared an independent schedule delay analysis.

USA – On behalf of the Baggage System Handling subcontractor in litigation for the Theodore F. Green International Airport project, prepared a damages claim.  

USA – On behalf of the subcontractor in litigation for a runway renovation project at an air force base in Maryland, prepared a delay analysis and expert report.

Thailand – Prepared a contractor tender baseline schedule for the new main terminal building at an airport in Bangkok.

USA – On behalf of the Contractor in litigation at the Eastern Airlines Maintenance Facilities renovation project at Miami International Airport, prepared a delay and damages expert report.

USA – On behalf of the Contractor in litigation at a Miami International Airport renovation project, prepared a delay and damages expert report related to the expansion of the airport central chiller plant.

USA – On behalf of the electrical subcontractor in arbitration at the Denver International Airport expansion project, prepared a lost productivity analysis and expert report.

Bank

Yugoslavia – On behalf of the Contractor for Raiffeisen Bank of Bosnia and Herzegovina, planning engineer services.

Cement Silo Storage Facility

USA – The Cement Storage Company Project in Mobile, Alabama. On behalf of the Contractor of this US$1 million project, retained as Project Engineer responsible for providing contractor baseline schedule, scheduling and project controls support, change order requests, and site supervision.

City Complexes

Qatar – On behalf of the Owner of Education City, a US$4bn, 12 square kilometre development project including infrastructure and various educational facilities and satellite campuses for eight international universities, retained as planning manager and overseeing claims.

Yugoslavia – On behalf of the Government for the Post-War Reconstruction and Rehabilitation Project of Sarajevo, Bosnia, and Herzegovina, a US$5bn programme for reconstruction of public works facilities and buildings damaged and destroyed by civil war; provided senior planning and project controls engineering services.

Yugoslavia – On behalf of the Government for the Post-War Reconstruction and Rehabilitation Project of Pristine, Kosovo, a US$2bn programme for reconstruction of public works facilities and buildings damaged and destroyed by civil war, provided senior planning and project controls engineering services.

Correctional Facility

USA – On behalf of the State of Ohio Department of Youth Services in litigation for the Marion Youth Detention Center project located in Marion, Ohio, appointed as Schedule Delay Expert to prepare a defense to a loss of productivity claim.

USA – On behalf of the Contractor for the 2500 bed Belmont Correctional Facility project located in Belmont, Ohio, prepared a delay, disruption, and acceleration cost claim.    

USA – On behalf of the State of Ohio Department of Youth Services for the Marion Youth Detention Center project, prepared a review of a claim submitted by an electrical contractor.

Data Center

USA – On behalf of the generator subcontractor for a data center in Colorado, prepared a delay analysis and expert report.     

Educational

USA – On behalf of a masonry subcontractor for a private collegiate school project in arbitration, prepared a schedule delay analysis.

Qatar – On behalf of the Contractor for two private secondary schools in dispute, prepared a schedule delay analysis and claim for extension of time and recovery of increased costs of performance.

USA – On behalf of the Monroe County School Board in Florida, retained to assess betterment and secondary costs associated with the Architect’s errors and omissions in the construction of two high schools, and presented the findings at mediation.

USA – On behalf of Broward County in Miami, Florida, retained to analyze a construction manager’s claims for delays, defective plans and specifications, and changes in the scope of work for the Miami Performing Arts Center.

USA – On behalf of the Broward County School Board in Florida, retained to provide litigation support in the assessment of damages and delays relating to the Architect’s delays, errors, and omissions in the construction of a high school.

USA – On behalf of a masonry subcontractor terminated for default on a school project.   Retained by counsel to prepare an assertive claim and assist with settlement discussions.

USA – On behalf of an electrical subcontractor in litigation for the South High Rise Dormitory renovation project located at Ohio State University in Columbus, Ohio, prepared a delay/disruption analysis.

USA – On behalf of Ohio Schools Facilities Commission in Columbus, Ohio, prepared a review of claims delay, compression, lost productivity, overtime impact, defective design drawings and indirect cost damages brought by an electrical contractor on a school construction project.

USA – On behalf of Bowling Green State University in Bowling Green, Ohio, appointed as Mediator for dispute brought by designer of a new Bureau of Criminal Investigation facility on the campus.

USA – On behalf of the Contractor for the University of Maryland Medical School Phase III project in Maryland, prepared a Time Impact Analysis claim.

USA – On behalf of the University of Cincinnati in Ohio, prepared a delay/disruption analysis of a claim submitted by a structural concrete contractor for a building project.

USA – On behalf of the State of Arkansas, Department of Education Division of Public Schools Academic Facilities and Transportation, retained as Cost Expert to prepare a costing model of the annual cost escalation for use in policy decisions determining the distribution of statewide funding for maintaining and updating state/local educational facilities.

USA – On behalf of the University of Toledo in Ohio, retained as Cost & Risk Expert to prepare a risk assessment of the contractor status on the Ottawa House Dormitory project.

USA – On behalf of Cleveland State University in Ohio in litigation, prepared a defense against a time and cost claim submitted by a contractor on a project.

USA – On behalf of the Ravenna School District in Ohio in litigation, prepared a defense against a time and cost claim submitted by a contractor on school project.

USA – On behalf of the Miami-Trace Local School District in Ohio in litigation, prepared a defense against a time and cost claim submitted by a contractor on a new high school project.

USA – On behalf of East Central College in Illinois in litigation, prepares a defense against a time and cost claim submitted by a contractor on a new sports complex project.

USA – On behalf of the Ottawa and Glandorf School District in Ohio in litigation, prepared a defense against a time and cost claim submitted by an electrical contractor on a new elementary/middle school project.

USA – On behalf of the Lakota Local School District in Ohio in litigation, prepared a defense against a time and cost claim submitted by an electrical contractor on a new elementary/middle/high school project.

USA – On behalf of the Wadsworth Local School District in Ohio in litigation, prepared a defense against a time and cost claim submitted by an electrical contractor on a new elementary/middle/high school project.

USA – On behalf of the Southern Local School District in Ohio in litigation, prepared a defense against a time and cost claim submitted by a general contractor on a high school expansion project.

USA – On behalf of the Crestline Exempted Village School District in Ohio in litigation, prepared a defense against multiple time and cost claims submitted by mechanical and electrical contractors on a new elementary/middle/high school project.

USA – On behalf of the University of Akron in Ohio in litigation, prepared a defense against multiple time and cost claims submitted by contractors on a school renovation project.

USA – On behalf of the University of Akron in Ohio in litigation, prepared a defense against time and cost claim submitted by electrical contractor on a school renovation project.

USA – On behalf of the University of Akron in Ohio in litigation, prepare a defense against wrongful termination claim submitted by contractor on a school stadium project.

USA – On behalf of the Cincinnati Public Schools in Ohio in litigation, prepare a defense against time and cost claims submitted by numerous contractors on a school project.

Embassy

Ecuador – On behalf of the Contractor renovating the United States Embassy in Ecuador in dispute before the US Federal Board of Appeals, prepared a schedule delay analysis and expert report. 

USA – On behalf of the Contractor renovating the Embassy of Spain in Washington D.C.in arbitration, prepared a schedule delay analysis and expert report.  

Federal Projects

USA – On behalf of the Contractor for the U.S. Government Services Administration’s renovation of the International Broadcast Bureau’s network control center located in Washington D.C., prepared an independent schedule delay analysis.

USA – On behalf of the U.S. Department of Homeland Security, Federal Emergency Management Agency (“FEMA”), retained as Cost Expert to estimate the costs of 165+ projects.  Projects consist of roads, buildings, equipment, and various ancillary categories.   Projects are located in the States of Arkansas, California, Illinois, Iowa, Louisiana, Minnesota, Missouri, Nebraska, North Carolina, Ohio, Oklahoma, South Carolina, South Dakota, and Texas. 

USA – On behalf of the Contractor for the U.S. Department of Energy’s National Nuclear Security Administration Highly Enriched Uranium Maintenance Facility expansion project in Oak Ridge, Tennessee, appointed as the Claims Consultant for the analysis of delay and disruption claims. 

USA – On behalf of the Contractor on a renovation project for the U.S. Department of Defense, Facilities Services Directorate, appointed as the Claims Consultant to prepare nine schedule delay analyses. 

Hospital & Medical Facilities

Qatar – On behalf of the control systems subcontractor on the largest hospital project in the Middle East, the USD$8 billion new-build Sidra Medical and Research Center in Doha, the 600-bed hospital project was in delay. Retained to lead a distressed project schedule recovery efforts including the development and implementation of field progress reporting tools for construction and commissioning works.

Canada – On behalf of the Consortium design/build contractor for the largest hospital project in North America, the USD 2.5 billion Centre Hospitalier de l’Université de Montréal (“CHUM”), the 772-bed hospital project was in delay.  Retained to prepare a schedule delay analysis and assisted with preparation of key time impact claims, and spearheaded production of a new baseline recovery schedule.

USA – On behalf the renovation Contractor for a Veterans Administration hospital project in North Carolina in litigation against the federal government, provided an independent schedule delay analysis and expert report.  

USA – On behalf of the University of Toledo located in Toledo, Ohio, in litigation, prepared an independent expert delay report.

USA – On behalf of the Contractor in litigation over the renovation and expansion of a Veterans Administration hospital in North Carolina, prepared a delay analysis and expert report. 

USA – On behalf of the University of Toledo located in Toledo, Ohio, in litigation, prepared independent expert report.

Hospitality

Jamaica – On behalf of the Jamaican Ministry of Finance for its development of an office and hotel complex, provided commercial management overseeing construction and defending the government against all claims.

USA – On behalf of the Architect of the Kauai Hyatt Regency Hotel in Hawaii in arbitration, prepared an independent schedule delay analysis.

USA – On behalf of the Contractor of the Regent Las Vegas Resort in Nevada, prepared a schedule delay analysis.

United Arab Emirates – On behalf of the Contractor of the Meydan Racecourse and Hotel Complex in arbitration, prepared a schedule delay analysis.

Indonesia – On behalf of the Contractor of the Kempinski Hotel in Jakarta, prepared a project recovery assessment.

Indonesia – On behalf of the golf course Contractor of the Royal Grading Golf Course and Country Club in settlement negotiations, prepared a schedule delay analysis.

Singapore – On behalf of the Contractor of the marina works for the Singapore Yacht Club in arbitration, prepared a schedule delay analysis.

Land Development

UAE – On behalf of the Contractor alleging wrongful termination from a mega development project in Dubai, UAE, prepared a delay analysis.

USA – On behalf of the Owner of a residential development project located in Virginia, prepared a completion costs and expert report for the default and termination of the site development contractor.

USA – On behalf of the Owner of a mixed use development project located in Maryland, appointed to review a claim submitted by the site development contractor.  

Multi Family

USA – On behalf of the Owner of a condominium project in Florida in litigation, prepared a delay and damages analysis expert report.

USA – On behalf of the Owner a condominium/commercial retail development project in litigation with insurers over a loss, prepared a delay analysis.

USA – On behalf of the Contractor in litigation on project to build a retirement facility in Virginia, prepare a claim against the bonding company of a defaulted mechanical subcontractor.

USA – On behalf of the Contractor for a pair of 42-story high-rise condominium projects in Florida, prepared a claim for equitable adjustment.

USA – On behalf of the Contractor for a pair of 10-story high-rise condominium projects in Florida, prepared a claim for equitable adjustment.

USA – On behalf of a glazing subcontractor for a high-rise condominium project in Washington D.C., prepared a claim for equitable adjustment.

Municipal

USA – On behalf of Noble County in Ohio in litigation, prepared a defense against a time and cost claim submitted by a contractor on a building project.

USA – On behalf of Bowling Green State University in Bowling Green, Ohio, appointed as Neutral to support mediator during hearing.   Designer of new Bureau of Criminal Investigation facility on the campus requested additional fees for the US$10.5 million project.

USA – On behalf of a site development subcontractor in litigation against the general contractor of the new Courthouse Complex project in Virginia, prepared a delay analysis and expert report.

USA – On behalf of the Contractor of a chemical storage facility project in Virginia in litigation, retained as Damages Expert arising due to a structural failure.

USA – On behalf of the steel erection subcontractor for a sports arena project in Iowa, prepared an independent schedule delay analysis.

USA – On behalf of the City of Fort Wayne, Indiana on a library renovation project, prepared an independent delay analysis.